Monday 8-25-08: There are 2 plumbers on site doing the underground layout for the saw cut company that will be out at the end of the week to saw cut and remove so the plumbers can start with the underground excavation at the beginning of next week. We are working on site with out a permit and will be unable to receive any inspections until we receive it. We expect to receive the permit no later than Tuesday of next week.
Tuesday 8-26-08: There are 2 plumbers on site working on connecting to the vents and determine what materials are needed to run the gas line from the end suite to our suite. They will be performing this work tomorrow and complete the work no later than Thursday.
Wednesday 8-27-08: NO BODY ON SITE TODAY. We are waiting to meet the property manager tomorrow to receive the key for the corner suite and the dog house above so we can run the gas line and also do the necessary work in the upper dog house with the traded involved with the project.
Thursday 8-28-08: Demoed out both existing bathrooms walls and flooring and stacked all debris in the corner to throw away in the dumpster that will be arriving tomorrow. The plumber was on site later in the day to complete the gas line connection in the end suite to find out the existing gas line threads are cross threaded and need to be fixed to make the point of connection. I got a hold of Brad my Project Manager and informed him of the problem and he got in touch with the property management which gave him the phone number of La Rue Plumbing the plumber that did the work on the site development to come out and fix there broken gas pipe. They got scheduled to be out Friday afternoon to fix there piping so my plumber can finish his work.
Friday 8-29-08: The saw cutter arrived at 7am to saw cut and remove the concrete so the plumber can install his underground plumbing pipes. It took him all day and while they where removing the concrete spoils they realized that they saw cut through 3 electrical pipes that where either run through the slab or right below the slab. We checked to make sure there was nothing in the pipes and took pictures of the damaged pipes and proceeded forward with our work. The 40 yard dumpster and Porto potty was also delivered today to site and I cleaned up all the demoed debris and through it into the dumpster. La Rue plumbing came out and fixed the gas pipe in the corner suite and the saw cutter will have to return tomorrow to do some minor jack hammering do to excessive footings at the demising wall and exterior walls.
Saturday 8-30-08: The saw cutter was on site today and jack hammered out the footings around the project and finished up on site early morning. Site was cleaned and we will be back on Tuesday to continue moving forward.