Monday, January 26, 2009

Decanter Construction Photo's




Decanter Construction Update 1.23.09

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update


MONDAY 1-19-09: Electrician on site today he installed transformers on top of back bar system for low voltage lighting connection. He also replaced light bulbs on site. Carpet installer on site today he finished installing carpet base in dinning room complete. Millworkers on site today they installed final piece of soffit, cabinet, and back splash for back bar system. They also installed toe kick, drawers, and bottom cabinet for POS station 1. They installed portion of toe kick for wine cabinet C, back splash for POS station 2, filler piece at hostess stand, and replaced ADA flip top at bar. Granite installer on site today he drilled hole in bar counter top per owners request for water machine plumbing.


TUESDAY 1-20-09: Millworkers on site today they temporarily installed lumigraph panels. Alarm co. on site today they finished installing alarm system complete. County building inspector on site today for final building inspection we have passed and have certificate of occupancy.


WEDNESDAY 1-21-09: Millworkers on site they finished installing toe kick on wine cabinet C. They also installed crown molding on POS station 2 and started molding on wine cabinet C. They installed low voltage lighting behind lumigraph and have made connection to transformers to make sure they are working properly. Cleaning crew on site today they cleaned site complete. Painter on site today they stenciled decanter logo on front wall as you walk into entrance. Soda machine installers on site today they started installing equipment for machine.


THURSDAY 1-22-09: Millworkers on site today they finished installing crown molding on wine cabinet C. They installed all doors drawers and pulls for cabinets. They also installed fill pieces underneath back bar countertop that rests on refrigeration units. Installer from Natura water started installing system.


FRIDAY 1-23-09: Millworkers on site today they installed glass for wine cabinet C. They painted another coat behind lumigraph panels and fastened and adjusted lighting and installed aluminum molding for panels. They also adjusted doors and drawers for cabinetry. Glass Co. on site today they started installing glass panels for wine bank and will return next week to finish installation. They have to reorder 5 panels to complete installation, glass supplier sent out wrong panels.


PROPOSED WORK FOR NEXT WEEK: Millworkers will be on site Monday of next week to complete punch list. Economy restaurant supply will be on site middle of week to install heat lamp in kitchen. Final Health inspection is scheduled for Monday. Electrician will be on site to install receptacle for heat lamp and install monopoint lights in bar. He will also adjust height on pendant lighting above banquet. Glass co. will be on site to finish installing glass for wine bank. We will be finished complete next week.

Thursday, January 22, 2009

Decanter Construction Photos 1.22.09




Decanter Construction Update 1.16.09

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update


MONDAY 1-12-09: Plumbers on site today they delivered and installed replacement parts for faucets in bathrooms. They fired up the water heater and cook line equipment everything is working properly. Patio and dinning room chairs were delivered to site. Wood works co. came out to site and picked up dining room table tops to refinish.


TUESDAY 1-13-09: Electrician on site today he installed door switch for air curtain, installed breaker for dishwasher, installed pendant lights and tested emergency lights. Millworkers on site today they installed counter top, step and shelving for back bar system. They installed ADA flip top at bar and finish panel on hostess stand. Wood works co. on site today they delivered and installed mirrors in bathrooms. Audio installer on site today he ran phone and internet lines into site. Fire security co. and fire sprinkler co. along with fire inspector on site today to test systems. All systems passed including emergency lighting.


WEDNESDAY 1-14-09: Granite co. on site today they drilled whole for light on hostess stand. They glued and clamped corner of granite at bar and caulked granite in bathrooms. Millworkers on site today they installed soffit for back bar and installed lights for lumigraphed areas. Audio installer on site today he started hooking up speakers he also hung television. Alarm co. on site today they installed system. Television co. on site they installed satellite and receiver. Mechanical worker on site he dropped register into wine cabinet C.


THURSDAY 1-15-09: Audio installers on site today they continued to install speakers and trim they also hooked up receiver and audio volume control panel. Painter on site today he touched up and finished paint complete. Granite co. on site today worker caulked back splash in bathrooms. Wood works co. on site today workers delivered and assembled table tops in dinning room along with trim and filler piece for booths. Glass installers on site today they laid out wine bank and cut and placed u channel for proper measurement of glass dimensions.


FRIDAY 1-16-09: Contractor on site finishing work to complete punch list. V-fire on set today worker prepped ansul system for test. Fire inspector on site today to test ansul system and system has passed and final fire inspection is complete.


PROPOSED WORK FOR NEXT WEEK: Millworkers will install the rest of cabinets complete. Electrician will finish wiring lighting for back bar system and he will be done complete. Designer will the rest of his finish delivered and installed. Glass wine bank glass should be delivered and installed complete by end of week. Final building inspection is scheduled for Tuesday. Final health inspection is scheduled for Thursday. We should be complete with all of construction by end of week.