Weekly Summary Update
MONDAY 1-19-09: Electrician on site today he installed transformers on top of back bar system for low voltage lighting connection. He also replaced light bulbs on site. Carpet installer on site today he finished installing carpet base in dinning room complete. Millworkers on site today they installed final piece of soffit, cabinet, and back splash for back bar system. They also installed toe kick, drawers, and bottom cabinet for POS station 1. They installed portion of toe kick for wine cabinet C, back splash for POS station 2, filler piece at hostess stand, and replaced ADA flip top at bar. Granite installer on site today he drilled hole in bar counter top per owners request for water machine plumbing.
TUESDAY 1-20-09: Millworkers on site today they temporarily installed lumigraph panels. Alarm co. on site today they finished installing alarm system complete. County building inspector on site today for final building inspection we have passed and have certificate of occupancy.
WEDNESDAY 1-21-09: Millworkers on site they finished installing toe kick on wine cabinet C. They also installed crown molding on POS station 2 and started molding on wine cabinet C. They installed low voltage lighting behind lumigraph and have made connection to transformers to make sure they are working properly. Cleaning crew on site today they cleaned site complete. Painter on site today they stenciled decanter logo on front wall as you walk into entrance. Soda machine installers on site today they started installing equipment for machine.
THURSDAY 1-22-09: Millworkers on site today they finished installing crown molding on wine cabinet C. They installed all doors drawers and pulls for cabinets. They also installed fill pieces underneath back bar countertop that rests on refrigeration units. Installer from Natura water started installing system.
FRIDAY 1-23-09: Millworkers on site today they installed glass for wine cabinet C. They painted another coat behind lumigraph panels and fastened and adjusted lighting and installed aluminum molding for panels. They also adjusted doors and drawers for cabinetry. Glass Co. on site today they started installing glass panels for wine bank and will return next week to finish installation. They have to reorder 5 panels to complete installation, glass supplier sent out wrong panels.
PROPOSED WORK FOR NEXT WEEK: Millworkers will be on site Monday of next week to complete punch list. Economy restaurant supply will be on site middle of week to install heat lamp in kitchen. Final Health inspection is scheduled for Monday. Electrician will be on site to install receptacle for heat lamp and install monopoint lights in bar. He will also adjust height on pendant lighting above banquet. Glass co. will be on site to finish installing glass for wine bank. We will be finished complete next week.