Tuesday, January 13, 2009

Decanter Construction Update 1.02.09

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update


MONDAY 12-29-08: Worker from V-FIRE on site today he installed wall mount manual pull for ansul system. He also started installing drops under hood for cook line equipment but will have to stop progress due to the change of cook line from original equipment plan by owner. V-fire will have to submit change order for work and be approved by owner before they can move forward. Mechanical worker on site today he adjusted slats on linear diffusers and installed register on face wall in front of site he also cut hole in ceiling and pulled duct through for air into wine cabinet. Nova security co. on site today they wired duct detectors together and wired up ansul system complete. Electrician on site today he turned on power and installed fixtures and finish trim. Painter on site today he continued painting doors and windows in front of site. Millworkers delivered P.O.S stations 1 and 2.


TUESDAY 12-30-08: Painter on site today he started painting doors and windows in kitchen he also painted windows outside in back of suite along with duct on roof for water heater. Millworkers on site today they installed both P.O.S stations.


WEDNESDAY 12-31-08: Painter on site today he prepped walls windows and doors for final coat. Millworkers on site today they installed wood trim along base of hostess stand and also applied cement board to face of stand and is ready for tile. Anchor construction co. on site today they installed replacement partition in women’s bathroom but there replacement partition is scratched and will have to be fixed. They could not install partition in men’s bathroom because they brought out wrong size they will come back out to site on Monday to finish.


THURSDAY 1-1-09: Painter on site today he sprayed final coat on doors and windows in front of house and is finished complete.


FRIDAY 1-2-09: Painter on site today he started to paint finish coats in dinning room and bar and prepped rest of site in front of house for finish coats. Economy restaurant supply on site today worker set dishwasher and tables in kitchen he also installed fan above back door. Plumber on site today they continued installing finish in kitchen and started installing plumbing for bathroom sinks. Tile worker on site today he finished setting and grouting tile in bathrooms and grouting base tile in dinning room and bar area.


SATURDAY 1-3-09: Painter on site he continued to paint final coats in front of site. Plumbers on site today they continued to install finish in kitchen bathrooms and bar. Tile worker on site today he installed tile on face of hostess stand he also finished laying base tile and grouting site. Contractors on site we installed foot rest for bar and trim under countertop. We also installed stairs for dry storage access.


PROPOSED WORK FOR NEXT WEEK: We will finish painting site complete. We will also finish all plumbing on site. We will also finish all electrical installation. Partitions in bathrooms and accessories will be installed complete. We will install hardware for all doors. Mechanical will finish all final installation and trouble shoot system. V-FIRE will be on site to finish ansul system complete. Granite installers will be on site to install countertop for hostess stand. Millworkers will be on site to finish installation of hostess stand both pos stations along with wine cabinet and back bar cabinets and ADA counter for bar. We will start to call for final inspection on all trades along with health inspection. We will also walk with owner for final punch list to be completed. Designer will start to have banquet tables chairs and all other décor to be supplied.