Decanter Construction Update 1.16.09

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update


MONDAY 1-12-09: Plumbers on site today they delivered and installed replacement parts for faucets in bathrooms. They fired up the water heater and cook line equipment everything is working properly. Patio and dinning room chairs were delivered to site. Wood works co. came out to site and picked up dining room table tops to refinish.


TUESDAY 1-13-09: Electrician on site today he installed door switch for air curtain, installed breaker for dishwasher, installed pendant lights and tested emergency lights. Millworkers on site today they installed counter top, step and shelving for back bar system. They installed ADA flip top at bar and finish panel on hostess stand. Wood works co. on site today they delivered and installed mirrors in bathrooms. Audio installer on site today he ran phone and internet lines into site. Fire security co. and fire sprinkler co. along with fire inspector on site today to test systems. All systems passed including emergency lighting.


WEDNESDAY 1-14-09: Granite co. on site today they drilled whole for light on hostess stand. They glued and clamped corner of granite at bar and caulked granite in bathrooms. Millworkers on site today they installed soffit for back bar and installed lights for lumigraphed areas. Audio installer on site today he started hooking up speakers he also hung television. Alarm co. on site today they installed system. Television co. on site they installed satellite and receiver. Mechanical worker on site he dropped register into wine cabinet C.


THURSDAY 1-15-09: Audio installers on site today they continued to install speakers and trim they also hooked up receiver and audio volume control panel. Painter on site today he touched up and finished paint complete. Granite co. on site today worker caulked back splash in bathrooms. Wood works co. on site today workers delivered and assembled table tops in dinning room along with trim and filler piece for booths. Glass installers on site today they laid out wine bank and cut and placed u channel for proper measurement of glass dimensions.


FRIDAY 1-16-09: Contractor on site finishing work to complete punch list. V-fire on set today worker prepped ansul system for test. Fire inspector on site today to test ansul system and system has passed and final fire inspection is complete.


PROPOSED WORK FOR NEXT WEEK: Millworkers will install the rest of cabinets complete. Electrician will finish wiring lighting for back bar system and he will be done complete. Designer will the rest of his finish delivered and installed. Glass wine bank glass should be delivered and installed complete by end of week. Final building inspection is scheduled for Tuesday. Final health inspection is scheduled for Thursday. We should be complete with all of construction by end of week.