Friday, October 24, 2008

Decanter Construction Photos






Decanter Construction Update Friday 10.24.08

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly summary update



MONDAY 10-6-08: Framers on site today they started framing wine bank soffit. Plumbers on site today they started installing floor drains and trap primers through site they also ran water through trench and stubbed up into bar wall. They removed rock from site as well. Electrician ran home runs into panel and set boxes in dinning room for pendant lights.

TUESDAY 10-7-08: Framers on site today they framed wine bank soffit and started framing lid around soffit. Plumbers continued installing floor drains and trap primers. Electricians laid out lighting in dinning room and installed light fixtures in dry storage area. Mechanical workers made poc from their duct to existing AC duct they also laid out penetration for duct into cubby above kitchen. Concrete workers on site today they drilled holes for rebar in trenches and have epoxied bar. They have tied 50% of rebar and will be back on site tomorrow to finish before inspection.

Wednesday 10-8-08: Framers continued frame hard lid in dinning room and around wine bank. Mechanical workers finished connecting duct to exhaust fans in bathrooms. They also cut penetration hole in kitchen for exhaust duct running up into cubby above. They also dropped in diffusers in dinning area and ran return air. Concrete co. is on site today to finish tying the rebar for concrete patch. Plumbers on site today to finish setting floor drains. Electrician tied main connections into j box.

THURSDAY 10-9-08: Concrete workers on sit today they poured concrete back into plumbing trenches. Plumbers on site today they installed mop sink and hooked up water main to site plumbing. Electrician on site today he ran conduit from data boxes to dry storage area.

FRIDAY 10-10-08: Framers on site today they finished framing lid in dinning room and around wine bank they also tied in soffit and barrel ceiling into lid. HVAC Company on site today they cut out and dropped in plenum for swap cooler on roof. They also installed inline exhaust fan in kitchen for hood and is ready for connection.

PROPOSED WORK FOR NEXT WEEK: We will finish framing by early next week and call for inspection for rough framing, rough electrical, and rough plumbing. We will then start installing light fixtures, dropping in fire sprinklers, and hanging drywall behind. Plumbers will be on site to install water heater and penetrate roof for venting duct and running water pipe into bar wall. HVAC Company will be on site next week as well to install swamp cooler on roof and hopefully install grease fan in kitchen and finish duct work for it.

Friday, October 3, 2008

Decanter Construction - September 2008

MONDAY 9-29-08: Framers on site today they finished framing soffits in dinning room and well wait to finish rest of framing until we get plumbing trenches closed. Mechanical workers on site today they installed exhaust fans I bathrooms and penetrated back wall for exhaust duct and is complete. They also made cut out in existing AC duct for connection but well wait to make point of connection until water condensing pipe from AC unit is relocated. They dropped in diffusers in dinning room as well. Electrician laid out lighting and ran more feeds into electrical panel.


TUESDAY 9-30-08: Electricians ran pipe and wire into wall at front of site where bar will be and also set boxes in place. Installer from MR.TINT came out to site today and applied white frost window tint to windows at front of building. I talked to water district today and will pick up signed approval form tomorrow morning at 8:00.I will also go to county tomorrow to pay and receive permits. Tomorrow at 10:00 electrician and I have a meeting with designer to figure out electrical circuitry for site and also get approval for emergency lighting.


WEDNESDAY 10-1-08: Electricians on site today they ran wire down front wall to boxes and are tied in. Had meeting with designer this morning and figured out electrical circuitry and emergency lighting and dimmer location. Went to county office today and pulled permits. Called for inspection tomorrow for underground plumbing and gas. Plumbers will be on site in morning to run test on plumbing to be ready for inspector.


THURSDAY 10-2-08: Electrician on site today he ran flex from pos station over ceiling to deck above bathroom for connection he also laid out emergency lighting. Plumbers are on site today they cleared trenches and got plumbing and gas lines up to test for inspection. Inspector came out to site today to give inspection for underground plumbing and gas and has passed us. Plumbers will be on site tomorrow to start backfilling trench.


FRIDAY 10-3-08: Electrician on site today he installed boxes and ran wire for emergency lighting. Plumbers on site today they started backfilling trenches. Installer from MR.TINT came out to site today to push all air pockets out of tint.


SATURDAY 10-4-08: Plumbers on site today they finished backfilling trenches and have started installing floor drains.

PROPOSED WORK FOR NEXT WEEK: Plumbers will continue installing floor drains and traps and run water supply through trench to bar. Concrete co. will be on site Tuesday to drill and epoxy per concrete patch detail for plumbing trenches. Framers will be on site Monday or Tuesday to finish rough framing. Electricians will be on site Monday to finish rough and should get fixtures delivered by middle of next week for installation. I will call for inspection for Wednesday to get rough plumbing and concrete patch detail passed we will also try to get rough framing and electrical passed at the same time.Thurday I will schedule for concrete to be poured back in trenches. Mechanical workers will be out next week to finish dropping in diffusers on site and install swamp cooler on roof. We should have site completely roughed in by end of week.