MONDAY 9-29-08: Framers on site today they finished framing soffits in dinning room and well wait to finish rest of framing until we get plumbing trenches closed. Mechanical workers on site today they installed exhaust fans I bathrooms and penetrated back wall for exhaust duct and is complete. They also made cut out in existing AC duct for connection but well wait to make point of connection until water condensing pipe from AC unit is relocated. They dropped in diffusers in dinning room as well. Electrician laid out lighting and ran more feeds into electrical panel.
TUESDAY 9-30-08: Electricians ran pipe and wire into wall at front of site where bar will be and also set boxes in place. Installer from MR.TINT came out to site today and applied white frost window tint to windows at front of building. I talked to water district today and will pick up signed approval form tomorrow morning at 8:00.I will also go to county tomorrow to pay and receive permits. Tomorrow at 10:00 electrician and I have a meeting with designer to figure out electrical circuitry for site and also get approval for emergency lighting.
WEDNESDAY 10-1-08: Electricians on site today they ran wire down front wall to boxes and are tied in. Had meeting with designer this morning and figured out electrical circuitry and emergency lighting and dimmer location. Went to county office today and pulled permits. Called for inspection tomorrow for underground plumbing and gas. Plumbers will be on site in morning to run test on plumbing to be ready for inspector.
THURSDAY 10-2-08: Electrician on site today he ran flex from pos station over ceiling to deck above bathroom for connection he also laid out emergency lighting. Plumbers are on site today they cleared trenches and got plumbing and gas lines up to test for inspection. Inspector came out to site today to give inspection for underground plumbing and gas and has passed us. Plumbers will be on site tomorrow to start backfilling trench.
FRIDAY 10-3-08: Electrician on site today he installed boxes and ran wire for emergency lighting. Plumbers on site today they started backfilling trenches. Installer from MR.TINT came out to site today to push all air pockets out of tint.
SATURDAY 10-4-08: Plumbers on site today they finished backfilling trenches and have started installing floor drains.
PROPOSED WORK FOR NEXT WEEK: Plumbers will continue installing floor drains and traps and run water supply through trench to bar. Concrete co. will be on site Tuesday to drill and epoxy per concrete patch detail for plumbing trenches. Framers will be on site Monday or Tuesday to finish rough framing. Electricians will be on site Monday to finish rough and should get fixtures delivered by middle of next week for installation. I will call for inspection for Wednesday to get rough plumbing and concrete patch detail passed we will also try to get rough framing and electrical passed at the same time.Thurday I will schedule for concrete to be poured back in trenches. Mechanical workers will be out next week to finish dropping in diffusers on site and install swamp cooler on roof. We should have site completely roughed in by end of week.