Friday, October 24, 2008

Decanter Construction Update Friday 10.24.08

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly summary update



MONDAY 10-6-08: Framers on site today they started framing wine bank soffit. Plumbers on site today they started installing floor drains and trap primers through site they also ran water through trench and stubbed up into bar wall. They removed rock from site as well. Electrician ran home runs into panel and set boxes in dinning room for pendant lights.

TUESDAY 10-7-08: Framers on site today they framed wine bank soffit and started framing lid around soffit. Plumbers continued installing floor drains and trap primers. Electricians laid out lighting in dinning room and installed light fixtures in dry storage area. Mechanical workers made poc from their duct to existing AC duct they also laid out penetration for duct into cubby above kitchen. Concrete workers on site today they drilled holes for rebar in trenches and have epoxied bar. They have tied 50% of rebar and will be back on site tomorrow to finish before inspection.

Wednesday 10-8-08: Framers continued frame hard lid in dinning room and around wine bank. Mechanical workers finished connecting duct to exhaust fans in bathrooms. They also cut penetration hole in kitchen for exhaust duct running up into cubby above. They also dropped in diffusers in dinning area and ran return air. Concrete co. is on site today to finish tying the rebar for concrete patch. Plumbers on site today to finish setting floor drains. Electrician tied main connections into j box.

THURSDAY 10-9-08: Concrete workers on sit today they poured concrete back into plumbing trenches. Plumbers on site today they installed mop sink and hooked up water main to site plumbing. Electrician on site today he ran conduit from data boxes to dry storage area.

FRIDAY 10-10-08: Framers on site today they finished framing lid in dinning room and around wine bank they also tied in soffit and barrel ceiling into lid. HVAC Company on site today they cut out and dropped in plenum for swap cooler on roof. They also installed inline exhaust fan in kitchen for hood and is ready for connection.

PROPOSED WORK FOR NEXT WEEK: We will finish framing by early next week and call for inspection for rough framing, rough electrical, and rough plumbing. We will then start installing light fixtures, dropping in fire sprinklers, and hanging drywall behind. Plumbers will be on site to install water heater and penetrate roof for venting duct and running water pipe into bar wall. HVAC Company will be on site next week as well to install swamp cooler on roof and hopefully install grease fan in kitchen and finish duct work for it.