Tuesday, December 16, 2008
Decanter Construction Update 12.12.08
Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 12-8-08: Painters on site today they finished painting first coat on all walls. Electrician on site today he installed 2x4 lights in kitchen and started finish trim in kitchen as well. I went to county office today to get revised electrical plans and bar soffit detail approved and was.
TUESDAY 12 -9-08: Painters on site today they continued to paint site. Electrician on site he continued to install finish trim in kitchen.
WEDNESDAY 12-10-08: Painters on site today they went sanded and patched walls through site to fix problem areas. They also prime coated back door and window in kitchen as well as two doors in water heater room. Fire protection co. on site today they installs trim for sprinklers and did walk through with inspector along with myself for above ceiling inspection in kitchen and has passed us.
THURSDAY 12-11-08: Electricians on site they continued to install finish trim on site and are 50 % done. They also finished wiring up panel complete and J boxes in cubby above. Tile workers on site today they finished grouting behind bar and started laying tile in entrance of site. HVAC co. on site today they installed louver in window above kitchen and started installing duct.
FRIDAY 12-12-08: Tile co. on site today they continued to install tile in bar dinning and bathroom areas. Mechanical workers on site today to take measurements for finishing duct work for grease fan.
SATURDAY 12-13-08: Tile co. on site today they continued to install tile in dinning room and bathrooms and are 90% done with tile and grouting on site.
PROPOSED WORK FOR NEXT WEEK: We will have granite counter tops installed in bar and bathrooms. Plumbers will install finish in bar and bathrooms and kitchen. Workers will install wallcovering bar wall and bathrooms. Workers will install partitions in bathrooms along with bathroom accessories. We will install doors and jams along with case for all doors and windows. We will also install stairs for dry storage access. Tile installers will be on site to finish tile complete.
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 12-8-08: Painters on site today they finished painting first coat on all walls. Electrician on site today he installed 2x4 lights in kitchen and started finish trim in kitchen as well. I went to county office today to get revised electrical plans and bar soffit detail approved and was.
TUESDAY 12 -9-08: Painters on site today they continued to paint site. Electrician on site he continued to install finish trim in kitchen.
WEDNESDAY 12-10-08: Painters on site today they went sanded and patched walls through site to fix problem areas. They also prime coated back door and window in kitchen as well as two doors in water heater room. Fire protection co. on site today they installs trim for sprinklers and did walk through with inspector along with myself for above ceiling inspection in kitchen and has passed us.
THURSDAY 12-11-08: Electricians on site they continued to install finish trim on site and are 50 % done. They also finished wiring up panel complete and J boxes in cubby above. Tile workers on site today they finished grouting behind bar and started laying tile in entrance of site. HVAC co. on site today they installed louver in window above kitchen and started installing duct.
FRIDAY 12-12-08: Tile co. on site today they continued to install tile in bar dinning and bathroom areas. Mechanical workers on site today to take measurements for finishing duct work for grease fan.
SATURDAY 12-13-08: Tile co. on site today they continued to install tile in dinning room and bathrooms and are 90% done with tile and grouting on site.
PROPOSED WORK FOR NEXT WEEK: We will have granite counter tops installed in bar and bathrooms. Plumbers will install finish in bar and bathrooms and kitchen. Workers will install wallcovering bar wall and bathrooms. Workers will install partitions in bathrooms along with bathroom accessories. We will install doors and jams along with case for all doors and windows. We will also install stairs for dry storage access. Tile installers will be on site to finish tile complete.
Monday, December 8, 2008
Decanter Construction Update 12.05.08
Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 12-1-08: Tile co. on site today they finished grouting tile in kitchen and also laid tile in bar area complete. Painter on site today he prepped site for primer.
TUESDAY 12-2-08: Painter on site today they sprayed primer on all paint surfaces complete. Kitchen equipment supplier on site today workers installed stainless steel sheets behind hoods in kitchen. Fire sprinkler co. on site today worker dropped sprinkler heads in kitchen and are complete and will schedule fire inspection as soon as possible.
WEDNESDAY 12-3-08: Drywaller on site today to hang piece of drywall and walk site to visually confirm area that need to be fixed before we can paint site with color. Mill worker on site today he installed Sub –Top for bar counter.
THURSDAY 12-4-08: Drywaller on site today he mudded problem areas on site. Mill worker on site today he installed sub-tops in bathrooms. Plumber on site today he turned on water to fill up water heater and to recheck for any leaks.
FRIDAY 12-5-08: Drywallers on site today they continued to mud problem areas. Granite installer on site today he measured sub-tops in bar and kitchen and made templates for them.
SATURDAY 12 -6-08: Drywaller on site today to give a finish sand and sponge of walls on site. Painter on site to finish sanding overspray and apply primer on site.
PROPOSED WORK FOR NEXT WEEK: Electrician will be on site next week to drop in 2x4 lights in kitchen and wire up panel complete. Mechanical workers will be on site to finish duct from frees fan window above kitchen in cubby. Painter will be on site to start painting finish coats on site. Tile installers will be right behind them to lay tile in dining room.
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 12-1-08: Tile co. on site today they finished grouting tile in kitchen and also laid tile in bar area complete. Painter on site today he prepped site for primer.
TUESDAY 12-2-08: Painter on site today they sprayed primer on all paint surfaces complete. Kitchen equipment supplier on site today workers installed stainless steel sheets behind hoods in kitchen. Fire sprinkler co. on site today worker dropped sprinkler heads in kitchen and are complete and will schedule fire inspection as soon as possible.
WEDNESDAY 12-3-08: Drywaller on site today to hang piece of drywall and walk site to visually confirm area that need to be fixed before we can paint site with color. Mill worker on site today he installed Sub –Top for bar counter.
THURSDAY 12-4-08: Drywaller on site today he mudded problem areas on site. Mill worker on site today he installed sub-tops in bathrooms. Plumber on site today he turned on water to fill up water heater and to recheck for any leaks.
FRIDAY 12-5-08: Drywallers on site today they continued to mud problem areas. Granite installer on site today he measured sub-tops in bar and kitchen and made templates for them.
SATURDAY 12 -6-08: Drywaller on site today to give a finish sand and sponge of walls on site. Painter on site to finish sanding overspray and apply primer on site.
PROPOSED WORK FOR NEXT WEEK: Electrician will be on site next week to drop in 2x4 lights in kitchen and wire up panel complete. Mechanical workers will be on site to finish duct from frees fan window above kitchen in cubby. Painter will be on site to start painting finish coats on site. Tile installers will be right behind them to lay tile in dining room.
Wednesday, December 3, 2008
Decanter Construction Update 11.28.08
Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 11-24-08: Drywallers on site today they continued to mud and sand walls and scraped and cleaned floors. Mechanical workers on site today they installed duct from hood to grease fan. They also installed registers in kitchen.
TUESDAY 11-25-08: Tile installers on site today they started laying tile on bathroom walls and will be on site tomorrow to continue.
WEDNESDAY 11-26-08: Tile installers on site today they continued to lay tile on bathroom walls and prepped kitchen and bar for tile.
THURSDAY 11-27-08: NOBODY ON SITE TODAY DO TO HOLIDAY.
FRIDAY 11-28-08: Tile installers on site today they grouted bathrooms and laid tile in kitchen.
SATURDAY 11-29-08: Tile installers on site today they laid tile in bar area and grouted kitchen and bar.
PROPOSED WORK FOR NEXT WEEK: We will have painter come out on Monday of next week to prime site and paint open ceiling in front of site. Drywallers will come out after to walk through and fix problem areas. After drywallers are done painters will come back out to site to continue. Stainless steel installers will be on site to apply stainless sheets in kitchen behind hoods. Mechanical workers will be on site to run duct for grease fan from window in cubby above kitchen to penetration.
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 11-24-08: Drywallers on site today they continued to mud and sand walls and scraped and cleaned floors. Mechanical workers on site today they installed duct from hood to grease fan. They also installed registers in kitchen.
TUESDAY 11-25-08: Tile installers on site today they started laying tile on bathroom walls and will be on site tomorrow to continue.
WEDNESDAY 11-26-08: Tile installers on site today they continued to lay tile on bathroom walls and prepped kitchen and bar for tile.
THURSDAY 11-27-08: NOBODY ON SITE TODAY DO TO HOLIDAY.
FRIDAY 11-28-08: Tile installers on site today they grouted bathrooms and laid tile in kitchen.
SATURDAY 11-29-08: Tile installers on site today they laid tile in bar area and grouted kitchen and bar.
PROPOSED WORK FOR NEXT WEEK: We will have painter come out on Monday of next week to prime site and paint open ceiling in front of site. Drywallers will come out after to walk through and fix problem areas. After drywallers are done painters will come back out to site to continue. Stainless steel installers will be on site to apply stainless sheets in kitchen behind hoods. Mechanical workers will be on site to run duct for grease fan from window in cubby above kitchen to penetration.