Wednesday, December 3, 2008

Decanter Construction Update 11.28.08

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update


MONDAY 11-24-08: Drywallers on site today they continued to mud and sand walls and scraped and cleaned floors. Mechanical workers on site today they installed duct from hood to grease fan. They also installed registers in kitchen.


TUESDAY 11-25-08: Tile installers on site today they started laying tile on bathroom walls and will be on site tomorrow to continue.


WEDNESDAY 11-26-08: Tile installers on site today they continued to lay tile on bathroom walls and prepped kitchen and bar for tile.


THURSDAY 11-27-08: NOBODY ON SITE TODAY DO TO HOLIDAY.


FRIDAY 11-28-08: Tile installers on site today they grouted bathrooms and laid tile in kitchen.


SATURDAY 11-29-08: Tile installers on site today they laid tile in bar area and grouted kitchen and bar.



PROPOSED WORK FOR NEXT WEEK: We will have painter come out on Monday of next week to prime site and paint open ceiling in front of site. Drywallers will come out after to walk through and fix problem areas. After drywallers are done painters will come back out to site to continue. Stainless steel installers will be on site to apply stainless sheets in kitchen behind hoods. Mechanical workers will be on site to run duct for grease fan from window in cubby above kitchen to penetration.