Tuesday, December 16, 2008

Decanter Construction Update 12.12.08

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update


MONDAY 12-8-08: Painters on site today they finished painting first coat on all walls. Electrician on site today he installed 2x4 lights in kitchen and started finish trim in kitchen as well. I went to county office today to get revised electrical plans and bar soffit detail approved and was.

TUESDAY 12 -9-08: Painters on site today they continued to paint site. Electrician on site he continued to install finish trim in kitchen.


WEDNESDAY 12-10-08: Painters on site today they went sanded and patched walls through site to fix problem areas. They also prime coated back door and window in kitchen as well as two doors in water heater room. Fire protection co. on site today they installs trim for sprinklers and did walk through with inspector along with myself for above ceiling inspection in kitchen and has passed us.


THURSDAY 12-11-08: Electricians on site they continued to install finish trim on site and are 50 % done. They also finished wiring up panel complete and J boxes in cubby above. Tile workers on site today they finished grouting behind bar and started laying tile in entrance of site. HVAC co. on site today they installed louver in window above kitchen and started installing duct.


FRIDAY 12-12-08: Tile co. on site today they continued to install tile in bar dinning and bathroom areas. Mechanical workers on site today to take measurements for finishing duct work for grease fan.


SATURDAY 12-13-08: Tile co. on site today they continued to install tile in dinning room and bathrooms and are 90% done with tile and grouting on site.


PROPOSED WORK FOR NEXT WEEK: We will have granite counter tops installed in bar and bathrooms. Plumbers will install finish in bar and bathrooms and kitchen. Workers will install wallcovering bar wall and bathrooms. Workers will install partitions in bathrooms along with bathroom accessories. We will install doors and jams along with case for all doors and windows. We will also install stairs for dry storage access. Tile installers will be on site to finish tile complete.