Monday, November 24, 2008

Decanter Construction Photos




Decanter Construction Update 11.21.08

Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update


MONDAY 11-17-08: Electrician on site today he pulled whip for wine display in entrance of site out of wall and set in to box in dry storage for future use. He also wired two monopoint lights entrance of site and ran conduit overhead. Drywallers on site today they continued to mud walls. Plumbers on site today they installed water heater. FRP co. on site today worker continued to install FRP in kitchen and will be on site tomorrow to finish complete.


TUESDAY 11-18-08: Drywallers on site today they continued to mud walls. Electrician on site today he ran whip in light cove around barrel ceiling in to box he also started wiring up panel. Plumbers on site today they hooked up water heater and ran vent pipe. FRP co. on site today they finished installing FRP complete.


Wednesday 11-19-08: Electrician on site today he ran conduit to roof for connection to make up air unit. He also ran connection from ansul switch to hood and continued to wire panel. Drywallers on site today they continued to mud walls. Mechanical workers on site today they installed old grease fan for point of reference for duct from hood. They also reset make up air unit after roofers patch penetrations. Roofing co. on site they patched all penetrations. Nova Security on site today they relocated fire alarm boxes to wall next to front entrance.


THURSDAY 11-20-08: Drywallers on site today they continued to mud and sand walls. Electrician on site today he ran wire to grease fan location and into box for later connection he also ran power to inline fan for dishwasher hood. Mechanical worker on site today he ran thermostat wire to box and is ready for hookup. He also started installing duct from hood to grease fan. Health inspector was on site today to do mid inspection.


FRIDAY 11-21-08: Drywallers on site today they continued to mud and sand walls. Mechanical worker on site today he installed skirt on one side of hood he also laid out and measured for duct for grease fan. Plumber on site today he rerouted vent pipe in kitchen so mechanical can run their grease fan duct. Audio installers on site today they ran wire to barrel ceiling speaker locations they also ran wire to down wall in kitchen for later outside connection.


PROPOSED WORK FOR NEXT WEEK: Drywallers will finish mudding and sanding walls. Tile installers will be out on Tuesday to start in bathrooms. We will call for above ceiling inspection after mechanical run grease duct and drop in diffusers in kitchen and after electrician installs lighting. Painter will be out next week to paint open ceiling and prime coat rest of site. Fire sprinkler co. will be on site to drop sprinklers in kitchen.

Wednesday, November 19, 2008

Decanter Construction Photos











Decanter Construction Update 11.17.08

MONDAY 11-10-08: Contractor on site today I installed plywood on framing for water heater and mop sink. Inspector on site today for screw inspection and has passed us. He also requested that architect engineer drawing for hanging soffit per build. Architect has been notified and has complied.


TUESDAY 11-11-08: Electricians on site today they installed receptacles in bar for audio installers per owners request and moved data and power boxes to new location. They also installed two emergency lights in site. Painter on site today to walk project.


WEDNESDAY 11-12-08: Drywallers on site today they hung the rest of drywall complete and started to tape and mud kitchen, bathrooms, and part of dinning room. Mechanical workers on site today they installed make up air unit on roof and installed skirt on top edge of hood. Electricians on site today they installed outlet in water heater room per owners request and started to install boxes in front of site for monopoint lights.


THURSDAY 11-13-08: Drywallers on site today they continued to tape and are 90% complete with taping. Electricians on site today they finished installing boxes for monopoint lights and have started to wire them. Designer and millworker on site today to walk with project manager and myself to clarify any issues and concerns on project.


FRIDAY 11-14-08: Drywallers on site today they continued to tape and mud walls. FRP installer on site today he started installing in kitchen and is about 25% complete. Electricians on site today they continued to wire up monopoint lights and are complete to j box in cubby above.

Decanter Construction Photos


Decanter Construction Update 11.7.08

MONDAY 11-3-08: Contractor on site today installed plywood deck above bathroom. No other contractors on site today. Framers will be on site starting Wednesday.


TUESDAY 11-4-08: Contractor on site today installed fur strips on front wall also installed ADA backing in bar and screwed off all backing in kitchen. Drywall hangers will be on site tomorrow to continue installing. Plumbers will be on site tomorrow as well. Audio installers will be on site tomorrow.


WEDNESDAY 11-5-08: Audio installers on site today they walked site with owner to finalize scope of work and began to pull data wire, telephone wire, and audio wire through site. Drywall hangers on site today they finished hanging drywall in dinning room and worked their way to front of site. Plumber on site today he made water pipe penetration through roof for swamp cooler and ran pipe to location. He also adjusted all floor drains on site to proper height. Inspector on site today to give screw inspection in kitchen and passed us.


THURSDAY 11-6-08: Drywallers on site today they continued hanging drywall in front of house and are 95% done and will hold off on the rest of board until audio installers run the rest of their wire and electrician installs receptacles for audio installers per owners request. Mechanical workers on site today they installed both hoods in kitchen.


FRIDAY 11-7-08: Drywallers on site today they hung drywall on face of hanging soffit in bar and face of soffit in dinning room and installed corner bead through site. Audio installers on site today they continued to pre wire site for future installation.