Wednesday, November 19, 2008

Decanter Construction Update 11.7.08

MONDAY 11-3-08: Contractor on site today installed plywood deck above bathroom. No other contractors on site today. Framers will be on site starting Wednesday.


TUESDAY 11-4-08: Contractor on site today installed fur strips on front wall also installed ADA backing in bar and screwed off all backing in kitchen. Drywall hangers will be on site tomorrow to continue installing. Plumbers will be on site tomorrow as well. Audio installers will be on site tomorrow.


WEDNESDAY 11-5-08: Audio installers on site today they walked site with owner to finalize scope of work and began to pull data wire, telephone wire, and audio wire through site. Drywall hangers on site today they finished hanging drywall in dinning room and worked their way to front of site. Plumber on site today he made water pipe penetration through roof for swamp cooler and ran pipe to location. He also adjusted all floor drains on site to proper height. Inspector on site today to give screw inspection in kitchen and passed us.


THURSDAY 11-6-08: Drywallers on site today they continued hanging drywall in front of house and are 95% done and will hold off on the rest of board until audio installers run the rest of their wire and electrician installs receptacles for audio installers per owners request. Mechanical workers on site today they installed both hoods in kitchen.


FRIDAY 11-7-08: Drywallers on site today they hung drywall on face of hanging soffit in bar and face of soffit in dinning room and installed corner bead through site. Audio installers on site today they continued to pre wire site for future installation.