Decanter Construction Update 11.17.08

MONDAY 11-10-08: Contractor on site today I installed plywood on framing for water heater and mop sink. Inspector on site today for screw inspection and has passed us. He also requested that architect engineer drawing for hanging soffit per build. Architect has been notified and has complied.


TUESDAY 11-11-08: Electricians on site today they installed receptacles in bar for audio installers per owners request and moved data and power boxes to new location. They also installed two emergency lights in site. Painter on site today to walk project.


WEDNESDAY 11-12-08: Drywallers on site today they hung the rest of drywall complete and started to tape and mud kitchen, bathrooms, and part of dinning room. Mechanical workers on site today they installed make up air unit on roof and installed skirt on top edge of hood. Electricians on site today they installed outlet in water heater room per owners request and started to install boxes in front of site for monopoint lights.


THURSDAY 11-13-08: Drywallers on site today they continued to tape and are 90% complete with taping. Electricians on site today they finished installing boxes for monopoint lights and have started to wire them. Designer and millworker on site today to walk with project manager and myself to clarify any issues and concerns on project.


FRIDAY 11-14-08: Drywallers on site today they continued to tape and mud walls. FRP installer on site today he started installing in kitchen and is about 25% complete. Electricians on site today they continued to wire up monopoint lights and are complete to j box in cubby above.