MONDAY 11-17-08: Electrician on site today he pulled whip for wine display in entrance of site out of wall and set in to box in dry storage for future use. He also wired two monopoint lights entrance of site and ran conduit overhead. Drywallers on site today they continued to mud walls. Plumbers on site today they installed water heater. FRP co. on site today worker continued to install FRP in kitchen and will be on site tomorrow to finish complete.
TUESDAY 11-18-08: Drywallers on site today they continued to mud walls. Electrician on site today he ran whip in light cove around barrel ceiling in to box he also started wiring up panel. Plumbers on site today they hooked up water heater and ran vent pipe. FRP co. on site today they finished installing FRP complete.
Wednesday 11-19-08: Electrician on site today he ran conduit to roof for connection to make up air unit. He also ran connection from ansul switch to hood and continued to wire panel. Drywallers on site today they continued to mud walls. Mechanical workers on site today they installed old grease fan for point of reference for duct from hood. They also reset make up air unit after roofers patch penetrations. Roofing co. on site they patched all penetrations. Nova Security on site today they relocated fire alarm boxes to wall next to front entrance.
THURSDAY 11-20-08: Drywallers on site today they continued to mud and sand walls. Electrician on site today he ran wire to grease fan location and into box for later connection he also ran power to inline fan for dishwasher hood. Mechanical worker on site today he ran thermostat wire to box and is ready for hookup. He also started installing duct from hood to grease fan. Health inspector was on site today to do mid inspection.
FRIDAY 11-21-08: Drywallers on site today they continued to mud and sand walls. Mechanical worker on site today he installed skirt on one side of hood he also laid out and measured for duct for grease fan. Plumber on site today he rerouted vent pipe in kitchen so mechanical can run their grease fan duct. Audio installers on site today they ran wire to barrel ceiling speaker locations they also ran wire to down wall in kitchen for later outside connection.
PROPOSED WORK FOR NEXT WEEK: Drywallers will finish mudding and sanding walls. Tile installers will be out on Tuesday to start in bathrooms. We will call for above ceiling inspection after mechanical run grease duct and drop in diffusers in kitchen and after electrician installs lighting. Painter will be out next week to paint open ceiling and prime coat rest of site. Fire sprinkler co. will be on site to drop sprinklers in kitchen.