Friday, January 30, 2009
Monday, January 26, 2009
Decanter Construction Update 1.23.09
Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 1-19-09: Electrician on site today he installed transformers on top of back bar system for low voltage lighting connection. He also replaced light bulbs on site. Carpet installer on site today he finished installing carpet base in dinning room complete. Millworkers on site today they installed final piece of soffit, cabinet, and back splash for back bar system. They also installed toe kick, drawers, and bottom cabinet for POS station 1. They installed portion of toe kick for wine cabinet C, back splash for POS station 2, filler piece at hostess stand, and replaced ADA flip top at bar. Granite installer on site today he drilled hole in bar counter top per owners request for water machine plumbing.
TUESDAY 1-20-09: Millworkers on site today they temporarily installed lumigraph panels. Alarm co. on site today they finished installing alarm system complete. County building inspector on site today for final building inspection we have passed and have certificate of occupancy.
WEDNESDAY 1-21-09: Millworkers on site they finished installing toe kick on wine cabinet C. They also installed crown molding on POS station 2 and started molding on wine cabinet C. They installed low voltage lighting behind lumigraph and have made connection to transformers to make sure they are working properly. Cleaning crew on site today they cleaned site complete. Painter on site today they stenciled decanter logo on front wall as you walk into entrance. Soda machine installers on site today they started installing equipment for machine.
THURSDAY 1-22-09: Millworkers on site today they finished installing crown molding on wine cabinet C. They installed all doors drawers and pulls for cabinets. They also installed fill pieces underneath back bar countertop that rests on refrigeration units. Installer from Natura water started installing system.
FRIDAY 1-23-09: Millworkers on site today they installed glass for wine cabinet C. They painted another coat behind lumigraph panels and fastened and adjusted lighting and installed aluminum molding for panels. They also adjusted doors and drawers for cabinetry. Glass Co. on site today they started installing glass panels for wine bank and will return next week to finish installation. They have to reorder 5 panels to complete installation, glass supplier sent out wrong panels.
PROPOSED WORK FOR NEXT WEEK: Millworkers will be on site Monday of next week to complete punch list. Economy restaurant supply will be on site middle of week to install heat lamp in kitchen. Final Health inspection is scheduled for Monday. Electrician will be on site to install receptacle for heat lamp and install monopoint lights in bar. He will also adjust height on pendant lighting above banquet. Glass co. will be on site to finish installing glass for wine bank. We will be finished complete next week.
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 1-19-09: Electrician on site today he installed transformers on top of back bar system for low voltage lighting connection. He also replaced light bulbs on site. Carpet installer on site today he finished installing carpet base in dinning room complete. Millworkers on site today they installed final piece of soffit, cabinet, and back splash for back bar system. They also installed toe kick, drawers, and bottom cabinet for POS station 1. They installed portion of toe kick for wine cabinet C, back splash for POS station 2, filler piece at hostess stand, and replaced ADA flip top at bar. Granite installer on site today he drilled hole in bar counter top per owners request for water machine plumbing.
TUESDAY 1-20-09: Millworkers on site today they temporarily installed lumigraph panels. Alarm co. on site today they finished installing alarm system complete. County building inspector on site today for final building inspection we have passed and have certificate of occupancy.
WEDNESDAY 1-21-09: Millworkers on site they finished installing toe kick on wine cabinet C. They also installed crown molding on POS station 2 and started molding on wine cabinet C. They installed low voltage lighting behind lumigraph and have made connection to transformers to make sure they are working properly. Cleaning crew on site today they cleaned site complete. Painter on site today they stenciled decanter logo on front wall as you walk into entrance. Soda machine installers on site today they started installing equipment for machine.
THURSDAY 1-22-09: Millworkers on site today they finished installing crown molding on wine cabinet C. They installed all doors drawers and pulls for cabinets. They also installed fill pieces underneath back bar countertop that rests on refrigeration units. Installer from Natura water started installing system.
FRIDAY 1-23-09: Millworkers on site today they installed glass for wine cabinet C. They painted another coat behind lumigraph panels and fastened and adjusted lighting and installed aluminum molding for panels. They also adjusted doors and drawers for cabinetry. Glass Co. on site today they started installing glass panels for wine bank and will return next week to finish installation. They have to reorder 5 panels to complete installation, glass supplier sent out wrong panels.
PROPOSED WORK FOR NEXT WEEK: Millworkers will be on site Monday of next week to complete punch list. Economy restaurant supply will be on site middle of week to install heat lamp in kitchen. Final Health inspection is scheduled for Monday. Electrician will be on site to install receptacle for heat lamp and install monopoint lights in bar. He will also adjust height on pendant lighting above banquet. Glass co. will be on site to finish installing glass for wine bank. We will be finished complete next week.
Thursday, January 22, 2009
Decanter Construction Update 1.16.09
Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 1-12-09: Plumbers on site today they delivered and installed replacement parts for faucets in bathrooms. They fired up the water heater and cook line equipment everything is working properly. Patio and dinning room chairs were delivered to site. Wood works co. came out to site and picked up dining room table tops to refinish.
TUESDAY 1-13-09: Electrician on site today he installed door switch for air curtain, installed breaker for dishwasher, installed pendant lights and tested emergency lights. Millworkers on site today they installed counter top, step and shelving for back bar system. They installed ADA flip top at bar and finish panel on hostess stand. Wood works co. on site today they delivered and installed mirrors in bathrooms. Audio installer on site today he ran phone and internet lines into site. Fire security co. and fire sprinkler co. along with fire inspector on site today to test systems. All systems passed including emergency lighting.
WEDNESDAY 1-14-09: Granite co. on site today they drilled whole for light on hostess stand. They glued and clamped corner of granite at bar and caulked granite in bathrooms. Millworkers on site today they installed soffit for back bar and installed lights for lumigraphed areas. Audio installer on site today he started hooking up speakers he also hung television. Alarm co. on site today they installed system. Television co. on site they installed satellite and receiver. Mechanical worker on site he dropped register into wine cabinet C.
THURSDAY 1-15-09: Audio installers on site today they continued to install speakers and trim they also hooked up receiver and audio volume control panel. Painter on site today he touched up and finished paint complete. Granite co. on site today worker caulked back splash in bathrooms. Wood works co. on site today workers delivered and assembled table tops in dinning room along with trim and filler piece for booths. Glass installers on site today they laid out wine bank and cut and placed u channel for proper measurement of glass dimensions.
FRIDAY 1-16-09: Contractor on site finishing work to complete punch list. V-fire on set today worker prepped ansul system for test. Fire inspector on site today to test ansul system and system has passed and final fire inspection is complete.
PROPOSED WORK FOR NEXT WEEK: Millworkers will install the rest of cabinets complete. Electrician will finish wiring lighting for back bar system and he will be done complete. Designer will the rest of his finish delivered and installed. Glass wine bank glass should be delivered and installed complete by end of week. Final building inspection is scheduled for Tuesday. Final health inspection is scheduled for Thursday. We should be complete with all of construction by end of week.
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 1-12-09: Plumbers on site today they delivered and installed replacement parts for faucets in bathrooms. They fired up the water heater and cook line equipment everything is working properly. Patio and dinning room chairs were delivered to site. Wood works co. came out to site and picked up dining room table tops to refinish.
TUESDAY 1-13-09: Electrician on site today he installed door switch for air curtain, installed breaker for dishwasher, installed pendant lights and tested emergency lights. Millworkers on site today they installed counter top, step and shelving for back bar system. They installed ADA flip top at bar and finish panel on hostess stand. Wood works co. on site today they delivered and installed mirrors in bathrooms. Audio installer on site today he ran phone and internet lines into site. Fire security co. and fire sprinkler co. along with fire inspector on site today to test systems. All systems passed including emergency lighting.
WEDNESDAY 1-14-09: Granite co. on site today they drilled whole for light on hostess stand. They glued and clamped corner of granite at bar and caulked granite in bathrooms. Millworkers on site today they installed soffit for back bar and installed lights for lumigraphed areas. Audio installer on site today he started hooking up speakers he also hung television. Alarm co. on site today they installed system. Television co. on site they installed satellite and receiver. Mechanical worker on site he dropped register into wine cabinet C.
THURSDAY 1-15-09: Audio installers on site today they continued to install speakers and trim they also hooked up receiver and audio volume control panel. Painter on site today he touched up and finished paint complete. Granite co. on site today worker caulked back splash in bathrooms. Wood works co. on site today workers delivered and assembled table tops in dinning room along with trim and filler piece for booths. Glass installers on site today they laid out wine bank and cut and placed u channel for proper measurement of glass dimensions.
FRIDAY 1-16-09: Contractor on site finishing work to complete punch list. V-fire on set today worker prepped ansul system for test. Fire inspector on site today to test ansul system and system has passed and final fire inspection is complete.
PROPOSED WORK FOR NEXT WEEK: Millworkers will install the rest of cabinets complete. Electrician will finish wiring lighting for back bar system and he will be done complete. Designer will the rest of his finish delivered and installed. Glass wine bank glass should be delivered and installed complete by end of week. Final building inspection is scheduled for Tuesday. Final health inspection is scheduled for Thursday. We should be complete with all of construction by end of week.
Tuesday, January 13, 2009
Decanter Construction Update 1.09.09
Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 1-5-09: Carpet installers on site they started laying carpet tile in dinning room they did not have proper transfer to tile they will be back tomorrow to finish. Anchor specialties on site today they finished installing replacement partitions in the bathrooms complete. Millworkers on site today they installed base for wine cabinet. Mechanical workers on site he installed registers on hard duct in front of site above bar he also landed wire for power disconnect for duct detectors and turned on units and adjusted thermostat to make sure they were working properly. Plumbers on site today they continued to install finish in bar, bathrooms and kitchen. Painter on site today he finished painting site complete. Mac faucets will ship out defective parts for faucets that plumber encountered when he installed. County inspector on site today to inspect 3m wrap on grease fan duct he also gave us gas release.
TUESDAY 1-6-09: Plumbers on site today they continued finish plumbing in kitchen, bathrooms, and bar and are complete they will return when new parts for faucets are delivered. Carpet installer finished laying carpet in dinning room he will have to return to finish carpet base he ran out of material. Contractors finished installing trim under bar countertop. Bases for tables were delivered today. Still waiting for SDGE to give us date for installing gas meter.
WEDNESDAY 1-7-09: Granite co. on site today they installed countertop for hostess stand. Restaurant equipment supply co. on site today they installed flashing behind bar equipment so they could set equipment to the wall and is complete. They also leveled refrigeration units in bar as well.
THURSDAY 1-8-09: Ansul installer on site today they finished drops for ansul system complete. Vendor for designer on site today they installed booths in dinning room and banquet on bar side of wine cabinet C. Fire inspection has been scheduled for Tuesday of next week. SDGE will be on site tomorrow to install gas meter for site.
FRIDAY 1-9-09: Electrician on site today he hard wired dishwasher complete wired up pig tail for glass washer in bar installed cover plates for lights and boxes changed out receptacle in kitchen for refrigerator. Millworker on site today he installed corbels and sub top for back bar system.
SATURDAY 1-10-09: Electricians on site today they installed contactors for air for hood labeled panels hooked up dimmer switch panels and checked electrical system complete to make sure system is fully operational. Millworkers on site they delivered the rest of wine cabinet c and installed it. They also delivered most of back bar cabinets.
PROPOSED WORK FOR NEXT WEEK: We will finish final punch list complete. Fire security co. will be out on Monday along with HVAC co. to do pre test of fire life safety system along with ansul system. Mechanical workers will also install register in wine cabinet C. We will have final fire inspection the next day. We will also have back bar system installed and electrician will finish wiring lighting for bar cabinets. We will have building final following fire and health final following that. We should have all finals next week and be ready to open doors for business. We will start construction of glass wine bank next week as well.
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 1-5-09: Carpet installers on site they started laying carpet tile in dinning room they did not have proper transfer to tile they will be back tomorrow to finish. Anchor specialties on site today they finished installing replacement partitions in the bathrooms complete. Millworkers on site today they installed base for wine cabinet. Mechanical workers on site he installed registers on hard duct in front of site above bar he also landed wire for power disconnect for duct detectors and turned on units and adjusted thermostat to make sure they were working properly. Plumbers on site today they continued to install finish in bar, bathrooms and kitchen. Painter on site today he finished painting site complete. Mac faucets will ship out defective parts for faucets that plumber encountered when he installed. County inspector on site today to inspect 3m wrap on grease fan duct he also gave us gas release.
TUESDAY 1-6-09: Plumbers on site today they continued finish plumbing in kitchen, bathrooms, and bar and are complete they will return when new parts for faucets are delivered. Carpet installer finished laying carpet in dinning room he will have to return to finish carpet base he ran out of material. Contractors finished installing trim under bar countertop. Bases for tables were delivered today. Still waiting for SDGE to give us date for installing gas meter.
WEDNESDAY 1-7-09: Granite co. on site today they installed countertop for hostess stand. Restaurant equipment supply co. on site today they installed flashing behind bar equipment so they could set equipment to the wall and is complete. They also leveled refrigeration units in bar as well.
THURSDAY 1-8-09: Ansul installer on site today they finished drops for ansul system complete. Vendor for designer on site today they installed booths in dinning room and banquet on bar side of wine cabinet C. Fire inspection has been scheduled for Tuesday of next week. SDGE will be on site tomorrow to install gas meter for site.
FRIDAY 1-9-09: Electrician on site today he hard wired dishwasher complete wired up pig tail for glass washer in bar installed cover plates for lights and boxes changed out receptacle in kitchen for refrigerator. Millworker on site today he installed corbels and sub top for back bar system.
SATURDAY 1-10-09: Electricians on site today they installed contactors for air for hood labeled panels hooked up dimmer switch panels and checked electrical system complete to make sure system is fully operational. Millworkers on site they delivered the rest of wine cabinet c and installed it. They also delivered most of back bar cabinets.
PROPOSED WORK FOR NEXT WEEK: We will finish final punch list complete. Fire security co. will be out on Monday along with HVAC co. to do pre test of fire life safety system along with ansul system. Mechanical workers will also install register in wine cabinet C. We will have final fire inspection the next day. We will also have back bar system installed and electrician will finish wiring lighting for bar cabinets. We will have building final following fire and health final following that. We should have all finals next week and be ready to open doors for business. We will start construction of glass wine bank next week as well.
Decanter Construction Update 1.02.09
Decanter Wine Lounge
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 12-29-08: Worker from V-FIRE on site today he installed wall mount manual pull for ansul system. He also started installing drops under hood for cook line equipment but will have to stop progress due to the change of cook line from original equipment plan by owner. V-fire will have to submit change order for work and be approved by owner before they can move forward. Mechanical worker on site today he adjusted slats on linear diffusers and installed register on face wall in front of site he also cut hole in ceiling and pulled duct through for air into wine cabinet. Nova security co. on site today they wired duct detectors together and wired up ansul system complete. Electrician on site today he turned on power and installed fixtures and finish trim. Painter on site today he continued painting doors and windows in front of site. Millworkers delivered P.O.S stations 1 and 2.
TUESDAY 12-30-08: Painter on site today he started painting doors and windows in kitchen he also painted windows outside in back of suite along with duct on roof for water heater. Millworkers on site today they installed both P.O.S stations.
WEDNESDAY 12-31-08: Painter on site today he prepped walls windows and doors for final coat. Millworkers on site today they installed wood trim along base of hostess stand and also applied cement board to face of stand and is ready for tile. Anchor construction co. on site today they installed replacement partition in women’s bathroom but there replacement partition is scratched and will have to be fixed. They could not install partition in men’s bathroom because they brought out wrong size they will come back out to site on Monday to finish.
THURSDAY 1-1-09: Painter on site today he sprayed final coat on doors and windows in front of house and is finished complete.
FRIDAY 1-2-09: Painter on site today he started to paint finish coats in dinning room and bar and prepped rest of site in front of house for finish coats. Economy restaurant supply on site today worker set dishwasher and tables in kitchen he also installed fan above back door. Plumber on site today they continued installing finish in kitchen and started installing plumbing for bathroom sinks. Tile worker on site today he finished setting and grouting tile in bathrooms and grouting base tile in dinning room and bar area.
SATURDAY 1-3-09: Painter on site he continued to paint final coats in front of site. Plumbers on site today they continued to install finish in kitchen bathrooms and bar. Tile worker on site today he installed tile on face of hostess stand he also finished laying base tile and grouting site. Contractors on site we installed foot rest for bar and trim under countertop. We also installed stairs for dry storage access.
PROPOSED WORK FOR NEXT WEEK: We will finish painting site complete. We will also finish all plumbing on site. We will also finish all electrical installation. Partitions in bathrooms and accessories will be installed complete. We will install hardware for all doors. Mechanical will finish all final installation and trouble shoot system. V-FIRE will be on site to finish ansul system complete. Granite installers will be on site to install countertop for hostess stand. Millworkers will be on site to finish installation of hostess stand both pos stations along with wine cabinet and back bar cabinets and ADA counter for bar. We will start to call for final inspection on all trades along with health inspection. We will also walk with owner for final punch list to be completed. Designer will start to have banquet tables chairs and all other décor to be supplied.
18021 Calle Ambiente #403
Rancho Sante Fe, CA 92067
Weekly Summary Update
MONDAY 12-29-08: Worker from V-FIRE on site today he installed wall mount manual pull for ansul system. He also started installing drops under hood for cook line equipment but will have to stop progress due to the change of cook line from original equipment plan by owner. V-fire will have to submit change order for work and be approved by owner before they can move forward. Mechanical worker on site today he adjusted slats on linear diffusers and installed register on face wall in front of site he also cut hole in ceiling and pulled duct through for air into wine cabinet. Nova security co. on site today they wired duct detectors together and wired up ansul system complete. Electrician on site today he turned on power and installed fixtures and finish trim. Painter on site today he continued painting doors and windows in front of site. Millworkers delivered P.O.S stations 1 and 2.
TUESDAY 12-30-08: Painter on site today he started painting doors and windows in kitchen he also painted windows outside in back of suite along with duct on roof for water heater. Millworkers on site today they installed both P.O.S stations.
WEDNESDAY 12-31-08: Painter on site today he prepped walls windows and doors for final coat. Millworkers on site today they installed wood trim along base of hostess stand and also applied cement board to face of stand and is ready for tile. Anchor construction co. on site today they installed replacement partition in women’s bathroom but there replacement partition is scratched and will have to be fixed. They could not install partition in men’s bathroom because they brought out wrong size they will come back out to site on Monday to finish.
THURSDAY 1-1-09: Painter on site today he sprayed final coat on doors and windows in front of house and is finished complete.
FRIDAY 1-2-09: Painter on site today he started to paint finish coats in dinning room and bar and prepped rest of site in front of house for finish coats. Economy restaurant supply on site today worker set dishwasher and tables in kitchen he also installed fan above back door. Plumber on site today they continued installing finish in kitchen and started installing plumbing for bathroom sinks. Tile worker on site today he finished setting and grouting tile in bathrooms and grouting base tile in dinning room and bar area.
SATURDAY 1-3-09: Painter on site he continued to paint final coats in front of site. Plumbers on site today they continued to install finish in kitchen bathrooms and bar. Tile worker on site today he installed tile on face of hostess stand he also finished laying base tile and grouting site. Contractors on site we installed foot rest for bar and trim under countertop. We also installed stairs for dry storage access.
PROPOSED WORK FOR NEXT WEEK: We will finish painting site complete. We will also finish all plumbing on site. We will also finish all electrical installation. Partitions in bathrooms and accessories will be installed complete. We will install hardware for all doors. Mechanical will finish all final installation and trouble shoot system. V-FIRE will be on site to finish ansul system complete. Granite installers will be on site to install countertop for hostess stand. Millworkers will be on site to finish installation of hostess stand both pos stations along with wine cabinet and back bar cabinets and ADA counter for bar. We will start to call for final inspection on all trades along with health inspection. We will also walk with owner for final punch list to be completed. Designer will start to have banquet tables chairs and all other décor to be supplied.
Thursday, January 8, 2009
Subscribe to:
Posts (Atom)